Can a Ministerial Directive Lawfully Withhold a Contractor’s Security Deposit After Expiry of the Defect Liability Period?

The High Court of Uttarakhand holds ministerial orders cannot override statutory defect liability timelines for municipal contracts, affirming local authority autonomy and offering persuasive guidance for future administrative disputes.

 

Summary

Category Data
CNR UKHC010007372025
Decision Date 27-08-2025
Disposal Nature DISPOSED
Judgment Author Hon’ble Mr. Justice Manoj Kumar Tiwari
Court High Court of Uttarakhand
Bench Single Judge
Questions of Law Whether a ministerial directive can lawfully withhold a contractor’s security deposit post-expiry of the defect liability period in municipal works?
Ratio Decidendi The minister has no authority to instruct a statutory local body to withhold a contractor’s security deposit where the work was completed satisfactorily and the defect liability period expired; financial irregularities of the authority do not justify withholding; the contractor is entitled to administrative recourse.
Facts as Summarised by the Court The petitioner, a registered contractor, completed civil works for Nagar Palika Parishad Mangloure in FY 2022-23 to the authority’s satisfaction. His one-year defect liability period expired without complaint. Despite no defects, a ministerial order directed retention of his 10% security deposit. A PIL alleged municipal financial irregularities.
Citations 2025:UHC:7602; WPMS No. 185 of 2025

What’s New / What Lawyers Should Note

  • Confirmation that ministerial orders cannot override statutory defect liability timelines in municipal contracts.
  • Clarification that absence of defects within the defect liability period entitles the contractor to release of security deposit.
  • Financial irregularities of a statutory authority are not a lawful basis to withhold a contractor’s security deposit.
  • Contractors may seek direct administrative recourse by representation to the Executive Officer within prescribed timelines.

Summary of Legal Reasoning

  1. The court clubbed petitions with common questions of law and fact, focusing on WPMS No. 185 of 2025 for detailed analysis.
  2. It noted that the one-year defect liability period had expired without any reported defects or complaints.
  3. The court examined the scope of a ministerial directive and held that a minister lacks authority to override or alter statutory timelines governing security deposits.
  4. It found that alleged financial irregularities by the municipal authority did not justify withholding a contractor’s deposit.
  5. The court directed the Executive Officer to consider the petitioner’s representation and pass a reasoned order within six weeks.

Arguments by the Parties

Petitioner

  • Completed awarded works in FY 2022-23 to the satisfaction of the municipal authority.
  • One-year defect liability period expired without any complaints.
  • Ten percent security deposit was unlawfully withheld based on a ministerial directive.

Respondent (Nagar Palika Parishad Mangloure)

  • Security deposit was withheld pursuant to an order of the Hon’ble Minister.
  • A PIL alleges financial irregularities by the municipal authority.

Factual Background

The petitioner, a registered petty contractor with Nagar Palika Parishad Mangloure, was awarded and completed various civil works in the 2022-23 financial year. His one-year defect liability period expired without any defects or complaints. Despite this, the municipal authority withheld his ten percent security deposit based on a ministerial directive amid unrelated PIL allegations of financial irregularities.

Statutory Analysis

The judgment interprets municipal contract provisions concerning the one-year defect liability period and security deposit retention. It clarifies that once the defect liability period ends and no defects are found, a statutory authority cannot retain the deposit. It further delineates the limits of executive or ministerial directions over statutory bodies, holding that ministerial orders cannot expand or alter statutory timelines or rights without express legislative empowerment.

Citations