Does a decree for specific performance become inexecutable for minor delays in deposit of the balance sale consideration, or can courts overlook hyper-technical defaults when readiness and willingness are evident?

 

Summary

Category Data
Court Supreme Court of India
Case Number C.A. No.-015069-015069 – 2025
Diary Number 35407/2022
Judge Name HON’BLE MR. JUSTICE SANJAY KAROL
Bench HON’BLE MR. JUSTICE SANJAY KAROL; HON’BLE MR. JUSTICE NONGMEIKAPAM KOTISWAR SINGH
Precedent Value Binding authority
Overrules / Affirms Affirms and clarifies existing precedents; overrules the High Court’s hyper-technical interpretation
Type of Law Civil – Specific Relief Act, contract law, execution procedure
Questions of Law
  • Does non-deposit of balance sale consideration within decree-fixed time rescind a contract automatically?
  • Can the executing court extend time under Section 28 without an application?
  • Does minor delay bar execution when readiness and willingness are proved?
  • How does the doctrine of merger apply to decrees in successive appeals?
Ratio Decidendi
  1. Section 28 empowers the court which passed a specific-performance decree to extend the time for deposit of sale money, but only upon an appropriate application—absence of such application does not ipso facto rescind the contract.
  2. A hyper-technical approach that treats every default as fatal must be avoided; delay must be assessed against the party’s overall conduct to determine genuine readiness and willingness.
  3. Non-payment of the balance sale consideration within the decree-fixed period does not amount to abandonment where the plaintiff’s conduct shows a continuing intention to perform.
  4. Under the doctrine of merger, the final operative decree of the appellate court supersedes the trial-court decree; only that decree is executable.
Judgments Relied Upon
  • V.S. Palanichamy Chettiar Firm v. C. Alagappan
  • Ramankutty Gupta v. Avara
  • Ram Lal v. Jarnail Singh
  • Balbir Singh v. Baldev Singh
  • Surinder Pal Soni v. Sohan Lal
  • Kunhayammed v. State of Kerala
  • Chandi Prasad v. Jagdish Prasad
Logic / Jurisprudence / Authorities Relied Upon
  • Section 28 SR Act empowers extension of time only by application in the same court
  • Hyper-technical forfeiture rejected (Ramankutty Gupta)
  • Real test is conduct showing readiness/willingness (Ram Lal)
  • Doctrine of merger allows only the final decree to remain operative (Balbir Singh)
Facts as Summarised by the Court
  • Agreement to sell land dated 11 Dec 2004; Rs.1 lakh earnest money
  • Trial Court (May 2011) decreed specific performance, directing sale deed within two months on payment of balance Rs.8.05 lakhs
  • First Appeal (Apr 2013) set aside decree; Second Appeal (Feb 2016) restored it
  • Execution petition filed on Day 87; balance paid on Days 138 and 245; HC dismissed execution for delay; SC allowed appeal and restored execution court order

Practical Impact

Category Impact
Binding On All subordinate courts in execution of specific-performance decrees
Persuasive For High Courts
Overrules High Court of Punjab & Haryana’s ruling that any delay beyond decree period is fatal
Distinguishes Surinder Pal Soni v. Sohan Lal; Raman Kutty cases (minor delays with no Section 28 move)
Follows Ramankutty Gupta v. Avara; Ram Lal v. Jarnail Singh; Balbir Singh v. Baldev Singh

What’s New / What Lawyers Should Note

  • Clarifies that non-payment of the balance sale consideration within the decree-fixed period does not ipso facto rescind the contract.
  • Emphasises that courts must eschew a hyper-technical approach and assess a party’s overall conduct to determine readiness and willingness.
  • Confirms that the executing court may only extend time under Section 28 upon a proper application; absence of such application does not invalidate the decree.
  • Reaffirms that the doctrine of merger renders only the final appellate decree operative for execution.
  • Provides binding guidance on minor-delay issues in specific-performance execution petitions.

Summary of Legal Reasoning

  1. Section 28 Scope

    • Decree-granting court can extend the time for deposit of sale money on application.
    • No automatic extension by mere filing of execution petition.
  2. Rejection of Hyper-Technical Forfeiture

    • Following Ramankutty Gupta, the Court rejects treating every delay as fatal.
    • Delay must be weighed against the decree-holder’s conduct.
  3. Readiness and Willingness Test

    • Reliance on Ram Lal: substantive proof of genuine intent to perform overrides minor defaults.
  4. Doctrine of Merger

    • Only the final appellate decree survives as the operative decree (Balbir Singh).
    • When the High Court set aside execution, no decree subsisted; SC’s restoration revives executability.
  5. Application to Facts

    • A 27-day delay beyond 60 days was minor and did not demonstrate refusal to perform.
    • No Section 28 application needed to preserve the contract where conduct shows intent.

Arguments by the Parties

Petitioner

  • Deposited nearly the full balance within a few months, showing readiness to perform.
  • Minor delay beyond two months should not defeat a substantive decree.
  • Section 28 allows extension—but even without a formal extension, conduct suffices.
  • Doctrine of merger renders the Trial Court decree unsuspended; execution is maintainable.

Respondent

  • Execution petition filed on Day 87—beyond the 60-day limit directed by the Trial Court.
  • No application under Section 28 was made to extend the time.
  • Failure to deposit balance sale consideration within two months bars execution.
  • Hyper-technical interpretation should lead to rescission of the contract.

Factual Background

In December 2004, the parties executed an agreement to sell a 2-biswa plot in Panchkula (Rs.9.05 lakhs total; Rs.1 lakh earnest money). The purchaser sued for specific performance in 2006; the Trial Court (May 2011) decreed performance, directing sale deed within two months on payment of Rs.8.05 lakhs. The First Appellate Court (2013) reversed that decree; the Second Appeal (2016) restored it. The purchaser filed execution on Day 87; balance deposits followed on Days 138 and 245. The High Court dismissed execution for delay; the Supreme Court allowed the appeal.

Statutory Analysis

  • Section 28, Specific Relief Act

    • Sub-sec (1): Allows vendor to apply for rescission if purchaser defaults within decree period or any extension.
    • Sub-sec (1) empowers the same court to extend time “on such terms as the court may allow.”
    • SC clarifies that extension power requires a formal application; yet non-grant does not auto-rescind a contract.
  • Doctrine of Merger

    • Only the final decree of the higher court remains operative (Surinder Pal Soni; Kunhayammed).
    • When execution petition is quashed by the High Court, no trial-court decree subsists until revived by final order.

Procedural Innovations

  • Endorses a purposive approach to execution defaults, focusing on substantive justice over technical compliance.
  • Clarifies the interplay between execution petitions and Section 28 applications in the same court.
  • Illustrates the application of the doctrine of merger to execution proceedings in successive appeals.

Alert Indicators

  • ✔ Precedent Followed – Affirms Ramankutty Gupta, Ram Lal, Balbir Singh principles.
  • 🔄 Conflicting Decisions – Resolves the High Court’s hyper-technical approach conflicting with prior Supreme Court rulings.

Leave a Reply

Your email address will not be published. Required fields are marked *

Recent Comments

No comments to show.